COMITE RIVER DIVERSION CHANNEL REACH 1
EAST BATON ROUGE PARISH, LA
Contract Value: $37,900,000 POP: 2023-Current
This $37,900,000 contract will involve the excavation of approximately one mile of the channel, placement of bedding material and riprap, demolition, clearing and grubbing, the relocation of a 48-inch sewer force main, cast-in-place structural concrete, and other associated features of work. Five-S will be self-performing all heavy civil earthwork and material supply while also directing the activities of numerous local subcontractors engaged in the performance of their specialties. Working together, the Five-S team is committed to extending our record of success on the CRDC and bringing this vital flood control project one step closer to completion. As of July 2024, Five-S is close to 30,000 labor hours and over 700,000 cubic yards of material have been excavated with zero OSHA recordable incidents.